In a design-build project, which statement is true?

Explanation:
In design-build, a single entity is contractually responsible for both design and construction, allowing design and construction work to overlap rather than follow a strict sequence. This integration speeds delivery and reduces client management burden because one team handles both sides of the project and coordinates decisions between design and build phases. The other descriptions fit design-bid-build rather than design-build: having the client contract with multiple specialized contractors implies separate design and construction contracts managed by the client, not a single design-build entity. Describing the process as sequential with separate contracts also aligns with design-bid-build, where design finishes before procurement and construction begin. Bidding after construction isn’t typical for standard project delivery methods, since procurement and selection happen before or during design to initiate construction.

In design-build, a single entity is contractually responsible for both design and construction, allowing design and construction work to overlap rather than follow a strict sequence. This integration speeds delivery and reduces client management burden because one team handles both sides of the project and coordinates decisions between design and build phases.

The other descriptions fit design-bid-build rather than design-build: having the client contract with multiple specialized contractors implies separate design and construction contracts managed by the client, not a single design-build entity. Describing the process as sequential with separate contracts also aligns with design-bid-build, where design finishes before procurement and construction begin. Bidding after construction isn’t typical for standard project delivery methods, since procurement and selection happen before or during design to initiate construction.